Canyon Road East - 99th Street Court East to 84th Street East (CRP 5726)

What’s Happening

Construction on a project to enhance safety and relieve traffic congestion on Canyon Road East between 99th Street Court East and 84th Street East began April 8, 2020. Work is expected to be complete in May 2022.

Photo of Canyon Road East near the 96th Street East intersection.
Image of the project vicinity map.

Project highlights


  • Canyon Road East from 96th Street East to 84th Street East was widened to five lanes, with two through lanes in each direction and a two-way left-turn lane. This section will have paved shoulders, curbs, gutters, and sidewalks.  
  • Canyon Road East from 99th Street Court East to 96th Street East was widened to four lanes, with two through lanes in each direction. This section has paved shoulders and barrier curbs on the west side, and curbs, gutters, and sidewalks on the east side. 
  • Traffic signals: 
    • A new traffic signal system was activated at the Canyon Road East and 96th Street East intersection June 3. 
    • The Canyon Road East and 84th Street East intersection was widened, and a reconstructed traffic signal system was activated to accommodate the future configuration. 
  • Other features: Street lighting, an enclosed storm drain system, and stormwater storage and treatment facilities were added as part of the project. 
Image of the proposed roadway section.

Contractor and funding

Rhino Construction is the contractor. The construction cost is approximately $8.9 million and is funded with County Road Funds, Traffic Impact Fees and Washington State Transportation Improvement Board Urban Arterial Program funds.

This project will support the planned Canyon Road Regional Connection Project. Learn more at www.canyonroadconnection.org.

Project Timeline

August 23, 2019: Bid Opening date


September 3, 2019: Pierce County awarded the contract to Rino Construction.


December 2019 to April 2020: Utility Relocation Phase


April 8, 2020:  Notice to Proceed


April 2020 to mid-2021: Construction underway (Winter suspension effective Jan. 11, 2021)


April 5, 2021:  Notice to Resume Work


July 2021: Majority of work is complete


August 30 through week of September 6, 2021: Minor work on Canyon Road East 


February 2022: Landscape maintenance period ends


April 2022: Final paving on the east leg of Canyon Road East and 84th Street East 


May 10, 2022:  Physical Completion


Right-of-Way Plans

Image of Right-of-Way Plans cover sheet.

Construction Plans (Sheets 1-60)

Image of Construction Plans cover sheet.

Construction Plans (Sheets 61-122)

Image of Construction Plans cover sheet.
Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd Street, Suite 109
Tacoma, WA 98409
Rino Construction
Contractor
Phone: (360) 469-4941
Address:
17937 Cedar Grove Road SE
Maple Valley, WA 98038