Canyon Road East - 208th Street East to 200th Street East (CRP 5764)

What’s Happening

Pierce County hosted the Pre-Construction Meeting on January 18, 2023, and issued the Notice to Proceed for March 20, 2023.  Work began March 20. The Contractor, SCI Infrastructure Inc., graded the site in preparation for the utility window that began July 10. 

The utility window is expected to continue through the beginning of 2024. At that point, the project is anticipated to be suspended for the winter until spring of 2024, when the contractor can complete the remainder of the project.


  Contact Information

Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913

Address:
2702 S 42nd Street, Suite 109
Tacoma, WA 98409

SCI Infrastructure Inc.
Contractor
Phone: (206) 242-0633


About the Project

  1. Overview
  2. Contract Information
  3. Project Timeline


Planned improvements to continue widening Canyon Road East from 208th Street East to 200th Street East (CRP 5764) include:

  • Extending Canyon Road East from 200th Street East to 208th Street East with one lane in each direction and a two-way left-turn lane.
  • Constructing concrete curb, gutter and sidewalk on the west side.
  • Constructing an enclosed storm drainage system, stormwater treatment and storage facilities.
  • Adding a traffic signal at the intersection of 208th Street East.
  • Modifying the existing signal system at 200th Street East intersection.
  • Adding street lighting.


Project Photos

Image of the road project before construction.
Image of the project vicinity map.
Image of the proposed roadway section.

Approved Right-of-Way Plans - 208th St E to 200 St E

Image of the project right-of-way plan cover sheet.

Approved Right-of-Way Plans - 192nd St E to 224th St E

Image of the project right-of-way plan cover sheet.