22nd Avenue East / 152nd Street East (CRP 5650)

What's Happening

Planting at the new stormwater detention pond on the south side of 152nd Street East was completed in early October 2019. Workers were onsite intermittently for the planting establishment period through mid-October 2020.

A new traffic signal system was activated at the 22nd Avenue East and 152nd Street East intersection in Spanaway on June 25, 2019. 


About the Project

 
Work on this project to improve safety and operations at the T-shaped intersection, which is located west of Naches Trail Elementary School, began in August 2018. 

In 2018, crews cleared portions of the project site, began widening the south side of 152nd Street East and built the stormwater detention pond. Utility companies also relocated utility lines.

Earlier in 2019, about 600 feet of 22nd Avenue East from where it intersects with 152nd Street East was rebuilt. Crews also constructed sidewalks along 22nd Avenue East and curb ramps at the intersection, installed new crosswalks, and added new street lights, curbs and gutters. 

Active Construction, Inc. is the project’s contractor. The construction cost is approximately $2,345,000 and is funded with County Road Funds.


Project Timeline



April 27, 2018: Bid Opening

June 4, 2018:
 Pierce County awarded the contract to 
Active Construction, Inc 

July 10, 2018:
 Pierce County hosted the Pre-Construction Meeting

August 1, 2018:
 Anticipated Notice to Proceed

October 1, 2018:  
Utility relocation window starts

June 25, 2019: Substantial Completion


Summer 2019: Physical Completion

Mid-October 2020: Planting establishment complete
Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913
Contractor: 
Active Construction, Inc.
Phone: (253) 248-1091
Address:
2702 S 42nd St, Ste 109
Tacoma, WA 98409
Address:
5110 River Rd E 
Tacoma, WA 98443