198th Avenue East - 144th Street East to 120th Street East (CRP 5675)

What’s Happening

Engineering: Brookfield Properties has completed the construction plans for Segment 2, and Pierce County has approved them.

Land: We continue to acquire the needed right-of-way between 128th Street East and 120th Street East.

Crews have completed grinding and new paving on 198th Avenue East in mid-October. Lane striping and illumination activities will follow by the end of November.  Until this work is complete the road will remain in its narrowed, current configuration. 


About the Project

  1. Overview
  2. Project Timeline


Improvements are planned to 1.5 miles of 198th Avenue East between 144th Street East and 120th Street East (CRP 5675). The project will be built in phases as Tehaleh development occurs and also accommodate future widening by Pierce County.

The initial, or Phase 1, project has been split into two segments:

  • Segment 1 will construct the roadway consisting of four lanes between 144th Street East and 128th Street East. The construction of segment 1 is complete.
  • Segment 2 will construct the roadway consisting of four lanes between 128th Street East and 120th Street East. The construction of segment 2 will begin in Spring 2021 within the existing right-of-way and any parcels that we have completed acquisition.


Project Photos

Image of the project vicinity map.
Image of the project.
Image of the project typical roadway section.
Right-Of-Way PlansImage of the project right-of-way plans cover sheet. Opens in new windowConstruction Plansundefined Opens in new window



Contact Us


Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913

Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409

Jim Kelly
Project Manager
Newland Communities
Phone: (253) 215-1964

Address:
505 S 336th St, Suite 430
Federal Way, WA 98003