Work to improve safety and traffic operations at the 92nd Avenue East and 224th Street East intersection began on Jan. 27 and is expected to run through spring 2023.
Utility relocation work began March 14 and runs through the fall.
About the Project
Planned improvements to the intersection of 92nd Avenue East / 224th Street East (CRP 5819) include:
Installing a traffic signal system
Adding an eastbound left-turn lane and westbound left-turn and right-turn lanes at the 92nd Avenue East / 224th Street East intersection.
Adding a two-way left-turn lane west of 90th Avenue East and between 90th Avenue East and 92nd Avenue East.
Installing concrete curb, gutter, and sidewalk.
Installing an enclosed storm drainage system, as well as stormwater treatment and storage facilities.
Installing street lighting.
Construction Schedule
Site preparation work ran from Jan. 27 through March 11. Utility relocation work will run from March 14 through the fall.
Once the utility relocation work is complete, construction work is expected to begin. A winter suspension of work is expected. The project is expected to be complete in spring 2023.
Traffic Impacts
Traffic may be shifted around work areas and detours for westbound traffic may be needed.
March 14-June 1 Utility Work
Utility relocation work in the project area is underway.
The following plan is expected to be in place through approximately June 1. This information may change. Please check this webpage for the latest information.
On Saturdays and Sundays:
Crews will work between 7 a.m. and 8 p.m. as needed
If crews are working, the road may be reduced to one lane with alternating traffic through the work zone. Flaggers will direct traffic.
The detour route will not be in place.
April 1 update about Monday-Friday work
On Friday, March 25, we moved the Monday-Friday westbound lane closure so it ran from just west of a group of businesses on the south side of 224th St. E about 0.4 miles west of SR 161 to 86th Ave. E. We made this change to accommodate westbound access to those businesses. We monitored the change, and have found that due to safety reasons, we need to move the start of the closure back to just west of the Graham Town Center entrance. This change will start Monday, April 4.
Please use the eastbound direction to enter and exit homes and businesses in the closure area when the detour is in place.
Monday to Friday:
Crews will work 7 a.m. to 8 p.m.
During work hours, the westbound lane of 224th St. E will be closed from just west of the Graham Town Center entrance to 86th Ave. E (see map), with a detour route in effect.
Those accessing the Graham Town Center can do so from westbound 224th St. E. After the entrance to the center, the westbound lane closure begins.
Westbound traffic will be detoured from State Route 161 to 232nd St. E to 86th Ave. E.
If crews are not working during those hours, the detour route won’t be in place. The detour may occasionally remain in place overnight.
The eastbound lane of 224th St. E will remain open.
Use the eastbound direction to enter and exit homes and businesses in the closure area when the detour is in place. You can also access the Graham Pierce County Library from 92nd Ave. E.
Contract Information
Funding
Pacific Civil & Infrastructure Inc. is the project contractor. The construction cost is approximately $3.2 million and is funded by federal Highway Safety Improvement Program funds.
Contract Plans
Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.