122nd Avenue East - 146th Street Court East to 136th Street East (CRP 5763)

What's Happening

Engineering: We are preparing the final engineering for the project.

Land: We are currently working with the adjacent property owners to acquire additional property rights needed to construct the project.

Image of the project vicinity map.
Image of the road project.

About the Project

Planned improvements of 122nd Avenue East from 146th Street Court East to 136th Street East are intended to enhance safety, increase capacity, and relieve traffic congestion. Improvements will include the following:

  • Expand to one northbound lane, a two-way left turn lane, and two southbound lanes.
  • Install cement concrete curb, gutter, and sidewalks.
  • Install an enclosed storm drainage system, and water quality treatment and storage facilities.
  • Install street lighting.
  • Install a new traffic signal system at 144th Street East.
Image of the proposed project roadway section.
Image of the project right-of-way plans cover sheet.

Project Timeline

May 2019 to May 2021: Complete preliminary engineering and right-of-way plans.

May 2021 to May 2024: Right-of-way acquisition, environmental permitting, produce final construction plans, engineer's estimate, and contract documents.

Early 2025: Advertise for Construction.