112th Street East - A Street South to 18th Avenue East (CRP 5686)
What's Happening Engineering: We are beginning the preliminary engineering for the project. We will be completing the field survey of the corridor, vertical alignment design, storm drainage treatment and conveyance design.
About the Project
Planned improvements to 112th Street South from A Street South to 18th Avenue East (CRP 5686) are intended to increase capacity and relieve traffic congestion, and include the following:
Expanding to five lanes with a two-way left-turn lane.
Adding paved shoulders, concrete curbs, gutters and sidewalks.
Adding street lighting.
Reconstructing the traffic signals at the 112th St E / Golden Given and 112th St E / 18th Ave E intersections.
Adding an enclosed storm drain system, as well as stormwater treatment facilities.
Project Timeline
September 2018 to December 2021: Complete preliminary engineering and right-of-way plans.
January 2022 and Beyond: Due to lack of funding this project is placed on hold.
Darin S. Cavanagh, P.E. Design Supervisor Phone: (253) 798-2284