Project Timeline
September 2017 to June 2020: Completed preliminary engineering and right-of-way plans.
June 2020 to February 2023: Right-of-way acquisition, environmental documentation, final design, construction plans, specifications, estimates, and contract advertisement.
Summer 2023: Construction