Olson Drive NW / 92nd Street NW - Key Center Sidewalks (CRP 5863)

What’s happening

Work on a project to install sidewalks on a section of Olson Drive Northwest started April 28. The work is expected to be completed in late June.


The 385-foot section is located to the west of the road’s intersection with Key Peninsula Highway Northwest near Key Center. Crews will also widen the road to accommodate new paved shoulders, and add curbs, gutters and storm drainage facilities. 


Work hours will be 7 a.m. to 3:30 p.m. Monday to Friday. The road may be reduced to one lane with alternating traffic during work hours.


Image of the project vicinity map.
CRP 5863 - Olson Dr KPN / 92nd St KPN

About the work

Utility relocation work was completed in last April.


Crews have installed temporary erosion control measures and cleared the site. Crews will widen the road and install storm drainage facilities through late May. From late May to late June, crews will install curbs, gutters and sidewalks. The road will be paved in late June.


The project’s contractor is Rodarte Construction. The construction cost is approximately $337,000 and is funded with County Road Funds and Washington State County Road Administration Board Rural Arterial Program Funds. 


Image of the project roadway section.
Image of the R/W Plan Cover Sheet.

Project Timeline

February 28, 2020: Bid Opening date


March 9, 2020: Pierce County awarded the contract to Rodarte Construction.


April 15, 2020: Pierce County hosted the Pre-Construction Meeting


April 28, 2020: Construction begins

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Engineering Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409

Rodarte Construction
Contractor
Phone: (253) 939-0532

Address:

17 East Valley Hwy E

Auburn, WA 98029