What's Happening
This project is complete.
About the Project
Improvements to 112th Street East from 18th Avenue East to 23rd Avenue East (CRP 5872) included resurfacing the roadway pavement and reconstructing curb ramps to current ADA accessibility standards. The contractor:
- Removed and repaved the top 2-inches of asphalt concrete pavement from 18th Avenue East to 23rd Avenue East.
- Replaced curb ramps at the 18th Avenue East, 22nd Avenue East, and 23rd Avenue East intersections with 112th Street East.
Improvements to the 112th Street East/Portland Avenue East intersection were completed within the last two years and are not included as part of this project.
Project Timeline
March 1, 2019: Bid Opening
March 18, 2019: Pierce County awarded the contract to Puget Paving and Construction
May 15, 2019: Pierce County hosted the Pre-Construction Meeting
June 24, 2019: Notice to Proceed
October 2, 2019: Substantial Completion
November 20, 2019: Physical Completion