Construction schedule
From Aug. 10-14, crews installed construction signage and prepared the site for the culvert work.
At the culvert location, crews widened the road shoulders, installed guardrails, and installed a wider box culvert that accommodates the roadway changes. The wider culvert will also improve fish passage.
Crews resurfaceed the roadway from late August to mid-September. In mid-September, the road was striped and centerline rumble strips were installed to alert motorists that they have started to cross the centerline.
In late September, traffic signs were installed and the roadside was restored.
The project’s contractor is Active Construction Inc. The construction cost is approximately $1.3 million and is funded with state Rural Arterial Program funds and federal Surface Transportation Program (Rural) funds.