Construction Schedule
Crews removed vegetation and debris from the project area July 13, 2020.
From mid-July to mid-August 2020, crews installed the enclosed storm drainage system. Crews installed the curbs, gutters, and sidewalks from mid-August to mid-September 2020.
Crews paved the roadway the week of Sept. 28, 2020. Through mid-October 2020, crews cleaned up the site, added landscaping, and striped the road and bike lanes.
The street lights, the flashing beacon and crosswalk were installed between Jan. 11 and Feb. 10, 2020.
The project’s contractor is Axum General Construction Inc. The construction cost is approximately $821,000. This project is funded with federal Surface Transportation Program (Urban) funds and County Road Funds.