Bridge #28210-A Seismic Retrofit - North Herron Road NW / Herron Bay (CRP 5794)

What’s Happening

A project to improve a North Herron Road Northwest bridge’s resistance to seismic events such as earthquakes and extend the bridge’s life started July 20. The work is expected to be completed by late September.


The 60-foot-long bridge is located on the Key Peninsula about 850 feet southeast of the Herron Island Ferry Dock. 

Traffic Impacts

Work will take place on weekdays. Work hours will typically be from 7 a.m. to 5 p.m. four days a week, although the schedule will be set to maximize work during low tides. 


Most of the work will take place underneath the bridge. The two-lane bridge may be reduced to one lane with alternating traffic during work hours.


Image of the project.
Image of the project vicinity map.

About the Project
Crews will clean the 10 concrete piles, which are posts that act as the legs of the bridge. Concrete-filled steel jackets will be placed around each pile to provide additional stability during seismic events.


The bridge was built in 1954 and carries approximately 350 vehicles a day, according to a 2013 vehicle count. The bridge is a three-span reinforced concrete flat slab bridge with precast concrete piles.


The project’s contractor is Nordvind Company. The construction cost is approximately $175,000. The project will be funded with Federal Highway Bridge Program funds.


Project Timeline

April 10, 2020: Bid Opening date


April 20, 2020: Pierce County awarded the contract to Nordvind Company


May 20, 2020: Pierce County hosted the Pre-Construction Meeting


July 20, 2020: Anticipated Notice to Proceed


September 1, 2020: Substantial Completion


September 30, 2020: Physical Completion

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd St., Suite 109
Tacoma, WA 98409

Nordvind Company
Contractor

Phone: (360) 825-5704

Address:

1720 Loraine St

Enumclaw, WA 98022