Military Road Interceptor

Military Road Sewer Interceptor project area map

About the project

Nearly 8,600 feet of new sewer pipe will be installed to support development along the Military Road East and 176th Street East corridor.

The project will extend sewer pipe along Military Road from 22nd Ave East to 36th Ave East. The project is anticipated to start early 2020 and take 12-18 months to complete. 

Expect intermittent road closures during construction. Emergency vehicle and local access will remain open at all times. Drivers should anticipate traffic delays.

Funding


  • Project #: P-110609
  • Estimated Cost: $5 million
  • Funding Source: Sewer utility funds
  • Construction Contractor: Miles Resources LLC

Timeline


  • Advertisement: Oct. 2019
  • Construction Completed: 2020
  • Duration: 12 -18 months

Project contacts

Steve Chanfrau, P.E

Engineering Manager
(253) 798-4129
[email protected]

Military Road Sewer project in Frederickson and Spanaway area.