Bridge #31221-A - Cramer Road NW / Glencove (5871)

What’s Happening

Engineering: Pierce County has completed a field survey and is in the final design stage.

Land: Right-of-Way needs will be evaluated.

Environmental: Necessary environmental permits are being obtained.

Image of the project vicinity map.
Project photo of the existing bridge.

About the Project

Planned improvements to Cramer Road Northwest at its crossing with Glencove (CRP 5871) are intended to improve safety and replace the existing bridge, including the following:

  • Remove the existing bridge.
  • Reconstruct a new bridge and approach roadways.
  • The new bridge will be two lanes with paved shoulders and constructed with pre-tensioned precast concrete girders.
  • Cramer Road Northwest will be closed during construction.
Image of the project right-of-way plans cover sheet.

Project Timeline

Fall 2018 to Winter 2021: Surveying, preliminary engineering and right-of-way plans.

Winter 2021 to Spring 2023: Right-of-way acquisition, environmental documentation, construction plans, specifications and estimates.

Summer 2023 to Summer 2024: Construction

Summer 2024: Open to traffic.