Cromwell Drive Northwest - Slope Stabilization (CRP 5866)

What’s Happening

A project to stabilize a 175-foot-long section of slope along Cromwell Drive Northwest started July 13. The majority of the work was completed Aug. 27. Minor work was completed Sept. 16.


The section is located on the north side of the road just east of 56th Avenue Court Northwest. 

Slope along Cromwell Drive that has been stabilized
Image of the project vicinity map.
Project photo of the covered existing hillside slope along the roadway.
Image of Right-of-Way plan set cover sheet.

About the Project

The slope had been sliding and failing over time. Black tarps were put into place to protect the slope from erosion and damage from rain events.


Crews removed the tarps and then cleared loose rock and soil from the slope. 


The slope was stabilized using shotcrete, an application method where a four-inch layer of concrete is sprayed onto the slope, matching its contours. Before the concrete was applied, crews installed metal bars across the slope to tie the concrete to the slope. 


Massana Construction is the project contractor. The construction cost is approximately $353,000 and is funded with County Road Funds.

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

May 5, 2021: Bid Opening date


May 24, 2021: Pierce County awarded the contract to Massana Construction


June 30, 2021: Pierce County hosted the Pre-Construction Meeting


July 13, 2021: Notice to Proceed


Aug. 27, 2021: Substantial Completion


Sept. 16, 2021: Physical Completion

Contact Us
Send a message arrow
Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913
Address:
2702 S 42nd Street,
Suite 109

Tacoma, WA 98409

Massana Construction
Contractor

Phone: (253) 313-5420

Address:

4810 Pt. Fosdick Drive NW, Suite 237

Gig Harbor, WA 98335