122nd Avenue East - 152nd Street East to 146th Street Court East (CRP 5895) 

What's Happening

Engineering: The project is in the early stages of the preliminary engineering phase.

Image of the project vicinity map.
Image of the project.

About the Project

Planned improvements to the 122nd Avenue East corridor from 152nd Street East to 145th Street East (CRP 5895) are intended to increase efficiency of the corridor and improve safety, and includes the following:


  • Adding a two-way left-turn lane and an additional southbound through lane.
  • Install cement concrete curb, gutter, and sidewalks.
  • Install an enclosed storm drainage system, and water quality treatment and flow control facilities.
  • Replace the existing traffic signal system.
  • Install street lighting.
Project Timeline

June 2019 to November 2021: Topographic survey work of the existing conditions, prepare preliminary construction plans, prepare a cost estimate, finalize right-of-way plans and complete the Preliminary Engineering Phase.


December 2021 to July 2024Right-of-way acquisition, environmental permitting, final engineering, and finalize construction documents.

August 2024 to May 2026: 
Construction, depending on funding.