28th Avenue East Pump Station

What's Happening


July 13 - November 13, 2020
The following road will be closed 24-hours per day:182nd Street East between 28th Avenue East and 34th Avenue East; and 28th Avenue East from 181st Street East to 183rd Street East. Local, business and emergency access will be provided.
Road closure July 13 - November 13 for 28th Avenue Sewer Pump Station project in Frederickson.

About the project

Sewer service will be extended to a 370-acre area. A new pump station will be installed at the intersection of 182nd Street East and 28th Avenue East. The pump station will move flows up and out of the basin and into the nearby gravity sewer system. Approximately 2,750 feet of force main will be installed in the public right-of-way west of the pump station.  Approximately 3,800 feet of gravity sewer will be installed east of the pump station along 182nd Street East and 38th Avenue East ending at 180th Street East.

This project supports the Pierce County Centers and Corridors initiative promoting compact communities built around major roadways. The project supports development along the 176th Street East corridor. This project will run simultaneously with the Military Road Interceptor project.

Timeline

  • Advertisement: Early 2020
  • Construction Start: June 2020
  • Duration: 9 - 12 months

How will this project affect you?

Homeowners: Connection requirements depend on the type of lot. There are two types of lots in the area of this work

  1. On-site septic system – Homes using approved on-site septic system until new development is proposed on the property; the existing septic system fails; or the owner chooses to connect.
  2. Vacant lots – Undeveloped lots will connect to the sewer system when developed.

For more information, please see Pierce County Code sections 13.04.030.B.2 and 18J.15.160.

Funding

  • Project #: P-110610
  • Estimated Total Project Cost: $7.25 million
  • Funding Source: New customer sewer connection fees
  • Construction Contractor: Tucci & Sons Inc.

Traffic impacts: Intermittent road closures will be necessary to complete the work. The contractor will always be required to maintain local and emergency vehicle access.

Privately owned property in County right-of-way: It is anticipated that the contractor will need to make use of the county right-of-way to install the sewer line. Property owners may need to remove privately owned items within the right-of-way that they wish to salvage prior to construction.

Average daily traffic in area

  • 14,100 cars per day on 22nd Ave East
  • 7,625 cars per day on 38th Ave East
  • 525 cars per day on 182nd St East

Project contacts

Aaron Callanan P.E
Design Engineering Supervisor 
(253) 798-4207 
aaron.callanan@piercecountywa.gov
Taran Bedi P.E. 
Project Engineer 
(253) 798-3082 
taran.bedi@piercecountywa.gov