28th Avenue East Pump Station

What's Happening 

July 1 Update
The Pierce County portion of the 28th Avenue East Pump Station project is nearing completion. Work within the public right-of-way for two private developments (Sierra Vista in 38th Avenue East; Prairie Oaks north of 182nd Street East near 30th Avenue East) is still ongoing. This project is an example of Pierce County's commitment to working with private development to achieve mutual goals.

P-110610 Project Website Update 210506

About the project

Pierce County extended its sewer service to a 370-acre area. Construction crews installed a new pump station at the intersection of 182nd Street East and 28th Avenue East. The pump station will move flows up and out of the basin and into the nearby gravity sewer system.

The project also included the installation of approximately 2,750 feet of force main in the public right-of-way west of the pump station and approximately 3,800 feet of gravity sewer east of the pump station along 182nd Street East and 38th Avenue East ending at 180th Street East.

This project supports the Pierce County Centers and Corridors initiative promoting compact communities built around major roadways. The project supports development along the 176th Street East corridor.


Timeline

  • Advertisement: Early 2020
  • Construction Start: June 2020
  • Duration: 9-12 months
  • Anticipated Construction End: August 2021
Funding

  • Project #: P-110610
  • Estimated Total Project Cost: $7.25 million
  • Funding Source: New customer sewer connection fees
  • Construction Contractor: Tucci & Sons Inc.

Project contacts

Jeff Roscoe, P.E
Construction Engineering Supervisor 
(253) 798-2119 
[email protected]

Evan Mann
Soundbuilt Homes
(253) 820-7835