Project Timeline
June 2021: Online open house.
June 2021 to December 2022: Complete field survey of the roadway, preliminary engineering, and right-of-way plans for the preferred option to reconfigure the intersection.
December 2022 and Beyond: Funding has not been identified for the right-of-way acquisition, environmental documentation, construction plans specifications, estimates, and construction. Those phases of the project will occur as funding becomes available.