May 5, 2021: Bid Opening date
June 15, 2021: Pierce County awarded the contract to Combined Construction.
July 28, 2021: Pierce County hosted the Pre-Construction Meeting
Sept. 1, 2021: Notice to Proceed
Oct. 7, 2021: Work complete on Group 2
Sept. 27, 2021 through Late May 2022: Material procurement suspension
Week of May 31, 2022: Work begins on Groups 1 and 3
June 30, 2022: Substantial Completion
August 4, 2022: Physical Completion