Bridge Deck Rehabilitations - Various Locations (CRP 5864)

What’s Happening

Resurfacing work on Group 2 was completed Oct. 7. 

About the Project

The project involves resurfacing bridge decks at various locations throughout the County. The locations include:


Group 1:
Bridge #12173-B
(304th Street East at
South Fork Muck Creek crossing)
The work has been postponed to Summer 2022 due to material manufacturing shortages. 
Image of the project vicinity map. Opens in new windowImage of project photo. Opens in new window
Group 2:
Bridge #17173-A
(16th Avenue South at
Lacamas Creek crossing)
This work was completed Oct. 7.
Image of the project vicinity map. Opens in new windowImage of project photo. Opens in new window
Group 3:
Bridge #33206-A
(Sumner Buckley Highway at
PSE Canal crossing)
The work has been postponed to Summer 2022 due to material manufacturing shortages
Image of the project vicinity map. Opens in new windowImage of project photo. Opens in new window

Project Timeline

May 5, 2021: Bid Opening date


June 15, 2021: Pierce County awarded the contract to Combined Construction.


July 28, 2021: Pierce County hosted the Pre-Construction Meeting


Sept. 1, 2021: Notice to Proceed


Sept. 27, 2021 through Summer 2022: Material procurement suspension

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409


Combined Construction
Contractor

Phone: (425) 610-4334

Address:

3701 South Road

Mukilteo, WA 98375