Bridge #6163-A - Harts Lake Road South / Horn Creek (CRP 5916)

What’s Happening

Engineering: Pierce County has completed a field survey and is in the preliminary design stage.

Land: Right-of-way needs will be evaluated.

Environmental: Necessary environmental permits will be obtained.

Image of the project vicinity map.
Image of project photo.

About the Project

Planned improvements to Harts Lake Road South at its crossing with Horn Creek (CRP 5916) are intended to replace the existing culvert, including the following:

  • Removing the existing 54" culvert.
  • Constructing a concrete structure. This structure will have two lanes with paved shoulders.
  • Approximately 550 feet of stream regrading and realignment.

Project Timeline

2023: Begin preliminary engineering, right-of-way plans and environmental documentation. Construction date to be determined.

Contact Us


Gary Amundsen, P.E.
Bridge Engineering Supervisor
Phone: (253) 798-2271

Address:
2702 S 42nd Street, Suite 109
Tacoma, WA 98409