Steele Street South / 102nd Street South (CRP 5849)

What’s Happening

A project to install a new traffic signal system at the Steele Street South and 102nd Street South intersection began Oct. 6. The signal was activated Nov. 19.


The addition of the signal is expected to improve traffic operations and safety at the intersection, which is located northeast of the I-5 and State Route 512 interchange.


Marked crosswalks were installed on all four legs of the intersection. 


Image of the project vicinity map.
Image of the project.

Construction schedule

Initially, crews removed vegetation from the site, along with two curb ramps. From mid-October to early November, they installed the pole foundations, the two replacement curb ramps and traffic signal components. 


Totem Electric is the contractor. The construction cost is approximately $404,000.

Project Timeline

April 3, 2020: Bid Opening date


April 14, 2020: Pierce County awarded the contract to Totem Electric


May 27, 2020: Pierce County hosted the Pre-Construction Meeting


October 6, 2020:  Notice to Proceed


Dec. 3, 2020: Project complete

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409


Totem Electric of Tacoma

Contractor

Phone: (253) 383-5022

Address:

2332 Jefferson Ave

Tacoma, WA 98402