ADA (Americans with Disabilities Act) Improvement Program - 2021 (CRP 5922)

What’s Happening

Construction on Group 1 began July 29, and was completed Aug. 17. Minor work took place through mid-September.


Construction on Group 2 began June 23 and was completed Aug. 17. Minor work took place through mid-September.




About the Project
Planned improvements are intended to improve accessibility and sidewalk connectivity.


The 2021 locations include:


Group 1:
Ainsworth Avenue South at
110 Street South
Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Group 2:
168th Street East
(Gem Heights Drive East to 171st Street Court East)
Image of the project vicinity map. Opens in new windowImage of the project.

Group 1 Improvements

About 90 feet of sidewalk were replaced along Ainsworth Avenue South north of the road’s intersection with 110th Street South. The new sidewalk is compliant with the Americans with Disabilities Act (ADA).


Crews were also install curb ramps that are compliant with the ADA on the north sides of the intersection.

Group 2 Improvements

Sections of sidewalk that are not in compliance with Americans with Disabilities Act (ADA) standards were removed and replaced on both sides of the road.


Curb ramps that are not in compliance with the ADA were removed and replaced with ADA-compliant curb ramps. Curb ramps were also be added at locations that didn't have ramps. 


New curbs and gutters were installed at sites where the sidewalks and curb ramps are replaced.

Contractor and funding

Sound Pacific Construction, LLC is the project contractor for both locations. The construction cost for both locations is approximately $465,000 and is funded with County Road Funds.

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

April 7, 2021: Bid Opening date


April 19, 2021: Pierce County awarded the contract Sound Pacific Construction LLC


June 3, 2021: Pierce County hosted the Pre-Construction Meeting


June 23, 2021: Work began on Group 2


July 29, 2021: Work began on Group 1


Aug. 17, 2021: Substantial Completion


Sept. 10, 2021: Physical Completion

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409

Sound Pacific Construction

Contractor

Phone: (253) 514-6226

Address:

6708 144th St NW Ste A

Gig Harbor, WA 98332