ADA (Americans with Disabilities Act) Improvement Program - 2022 (CRP 5923)

What’s Happening
Engineering: We are continuing the engineering for the project. We have completed the field survey of the existing curb ramps and sidewalks throughout the project limits.


Land: Additional right-of-way needs are being assessed.

About the Project
Planned improvements for the ADA Improvement Program - 2022 (CRP 5923) are intended to improve accessibility and will include the following:


Image of the project vicinity map. Opens in new window
Group 1:
159th Street East / 160th Street East
(300' E/O B Street East to
7th Avenue Court East)
  • Improve accessibility to sidewalks.
  • Removing and reconstructing existing curb ramps and sidewalks within the project area that do not meet ADA requirements.
  • Adding new curb ramps within the project area where needed.
Image of the project vicinity map. Opens in new windowGroup 2:
82nd Avenue East / 224th Street East
  • Improve accessibility to the pedestrian pushbutton on the Northeast corner
Image of the project right-of-way plans cover sheet. Opens in new windowRight-of-Way Plans
Project Timeline

May 2020 to July 2020Complete field surveys. 


July 2020 to December 2021: Complete engineering and environmental documentation.


January 2022 to March 2022: Complete construction plans, specifications, and estimates.


Summer 2022: Construct improvements.