2021 Asphalt Overlay Program (CRP 5912)

What's Happening

Planned improvements for the 2021 Asphalt Overlay Program (CRP 5912) involves resurfacing the existing pavement and upgrading existing curb ramps to meet ADA standards at various locations throughout the County. The locations include:


Group 1:
192nd Street East
(B Street East to 22nd Avenue East)

Crews will remove sidewalks and curb ramps that are out of compliance with the Americans with Disabilities Act and replace them with those that are in compliance the week of July 19. Utility work will also take place.


Work hours are 7 a.m. to 3:30 p.m. Monday to Friday. The road may be reduced to one lane with alternating traffic between 7 a.m. and 3 p.m. 



Image of group 1 project location. Opens in new windowImage of group 1 location. Opens in new window
Group 2:
85th Street East
(Mckinley Avenue East to Portland Avenue East)
Upgrades to the traffic signal systems and curb ramps will take place July 19-Aug. 6.

Work hours are 7 a.m. to 4 p.m. Monday to Friday. The road may be reduced to one lane with alternating traffic during work hours.
Image of group 2 project location. Opens in new windowImage of group 2 location. Opens in new window
Group 3:
Waller Road East
(112th Street East to 72nd Street East)

Upgrades to the traffic signal system and curb ramps will be made at the Waller Road East and 112th Street East intersection July 19 through Aug. 6. Upgrades to the curb ramps at the Waller Road East and 104th Street East intersection will also take place. Utility work is expected to take place the week of July 19.


Work hours are 7 a.m. to 3:30 p.m. Monday to Friday. Motorists should expect delays. The road may be reduced to one lane with alternating traffic between 7 a.m. and 3 p.m.



Image of group 3 project location.Image of group 3 location. Opens in new window
Group 4:
Golden Given Road East
(112th Street East to 72nd Street East)

Utility work will take place the weeks of July 26 and Aug. 2.


Work hours are 7 a.m. to 3:30 p.m. Motorists should expect delays. The road may be reduced to one lane with alternating traffic between 7 a.m. and 2 p.m.



Image of group 4 project location. Opens in new windowImage of group 4 location. Opens in new window

Contractor

Miles Resources LLC is the project contractor.

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

March 31, 2021: Bid Opening date


April 9, 2021: Pierce County awarded the contract to Miles Resources


April 27, 2021: Pierce County hosted the Pre-Construction Meeting


June 14, 2021:  Notice to Proceed date

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409

Miles Resources LLC
Contractor

Phone: (253) 383-3585

Address:

400 Valley Avenue NE

Puyallup, WA 98372