8th Avenue East - 336th Street East to 288th Street East (CRP 5898)

What’s Happening

Work to resurface 8th Avenue East from 336th Street East to 288th Street East began April 11. The project is expected to be complete by late May.

Site preparation work took place the week of April 11. Work resumed the week of May 2 after being delayed due to weather. 

Paving work is complete. Remaining work is expected to run through mid-June. This work is weather dependent.

  Contact Information

Andrew Davis, P.E.
Construction Supervisor
Phone: (253) 798-6913

Address:
2702 S 42nd Street, Suite 109
Tacoma, WA 98409


Image of the project vicinity map.
Image of the road project.


About the Project

  1. Overview
  2. Traffic Impacts
  3. Contractor & Cost
  4. Project Timeline

Planned improvements to 8th Avenue East from 336th Street East to 288th Street East (CRP 5898) involve resurfacing the existing asphalt pavement and installing approximately 200 feet of guardrail approximately 400 feet south of 288th Street East.