8th Avenue East - 336th Street East to 288th Street East (CRP 5898)

What’s Happening

Work to resurface 8th Avenue East from 336th Street East to 288th Street East began April 11. The project is expected to be complete by late May.


Site preparation work took place the week of April 11. Work resumed the week of May 2 after being delayed due to weather. 


Paving work is complete. Remaining work is expected to run through mid-June. This work is weather dependent.

Image of the project vicinity map.
Image of the road project.

About the Project
Planned improvements to 8th Avenue East from 336th Street East to 288th Street East (CRP 5898) involve resurfacing the existing asphalt pavement and installing approximately 200 feet of guardrail approximately 400 feet south of 288th Street East.

Traffic Impacts

Work hours will be 7 a.m. to 3:30 p.m. Monday to Friday.


The two-lane road may be reduced to one lane with alternating traffic.

Contractor and Cost

Puget Paving & Construction Inc. is the project’s contractor. The construction cost is approximately $790,000 and is funded with federal Surface Transportation Program funds and County Road Funds.

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

July 14, 2021: Bid Opening date


July 21, 2021: Pierce County awarded the contract to Puget Paving & Construction Inc.


March 10, 2022: Pierce County hosted the Pre-Construction Meeting


April 4, 2022: Notice to Proceed


July 7, 2022: Physical Completion

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Contractor

Puget Paving & Construction Inc.

Phone: (253) 474-5616

Address

2702 S 42nd Street, Suite 109

Tacoma, WA 98409

Address

10910 26th Ave S

Lakewood, WA 98499