ADA (Americans with Disabilities Act) Improvement Program - 2023 (CRP 5934)

What’s Happening
Engineering: We are preparing the final engineering for the project.

About the Project
Planned improvements for the ADA Improvement Program - 2023 are intended to improve accessibility and sidewalk connectivity at various locations throughout the County, and include the following:

  • Removing and reconstructing existing curb ramps.
  • Adding new curb ramps where needed.
  • Evaluating sidewalks within the project area that do not meet ADA requirements.

The locations include:

Image of the project group vicinity map. Opens in new windowGroup 1:
Tule Lake Road South
(Spanaway Loop Road South to Ainsworth Avenue South)
Image of the project group vicinity map. Opens in new windowGroup 2:
136th Street East
(99th Avenue Court East to 103rd Avenue East)
Image of the project group vicinity map. Opens in new windowGroup 3:
168th Street East
(119th Avenue Court East to 122nd Avenue East)
Project Timeline

May 2021 to July 2021Completed field surveys. 

July 2021 to December 2022: Complete engineering and environmental documentation.

January 2023 to March 2023: Complete construction plans, specifications, and estimates.

Summer 2023: Construct improvements.