Parkland/Brookdale Interceptor Phase 3

Parkland/Brookdale Interceptor Phase 3 Construction Map Opens in new window

About the project

This project is the third of multiple phases necessary to provide increased capacity for the Parkland/Brookdale Interceptor. The existing 36-inch sewer interceptor between phase 2 and the future interceptor phases is expected to reach its capacity by the end of 2024.

To address that capacity need and to build a system that will last well into the future, Pierce County is constructing a 72-inch interceptor that will convey wastewater from the intersection of 131st Street East and A Street South to an existing sewer interceptor at 129th Street South and C Street South.

Future phases of the project will address other capacity issues in the existing system. 

The targeted project completion date is October 2023.

Project contact

Tami Vogel
Construction Engineer
(253) 798-3088
[email protected]

Juan Loyola, PE
Construction Engineering Supervisor
(253) 798-2281

[email protected]

Traffic impacts

This project will include seven different work zones. The contractor working for Pierce County on the Parkland/Brookdale Sewer Interceptor Phase 3 project completed work for Section B in November 2022.
 
Pierce County also approved the contractor’s request to suspend construction activities due to high groundwater levels. The remaining work for Sections C, E and G is anticipated to resume in July 2023. We will provide more information prior to work starting back up next summer. 

Road Closure Schedule

SectionClosure DatesLocation
ACompleted
Intersection of C Street South and Tule Lake Road South
FCompleted
Tule Lake Road between Route 7 and A Street South
DCompleted129th Street South between C Street South and Route 7
BCompletedC Street South between Tule Lake Road and 128th Street South 
E*Summer 2023129th Street South between Route 7 and A Street South
C*Summer 2023West side of Route 7
C*Summer 2023East side of Route 7
G*
Summer 2023A Street South at 131st Street South

*Tentative schedule. May be subject to change. Some work, including final pavement restoration, will be completed after all other phased activities are complete. Final restoration work is weather dependent.  

  1. Timeline
  2. Funding
  3. What is a sewer interceptor?
  4. What does this mean for me?

Timeline


Advertisement: Early 2022

Contract Awarded: May 2022

Construction Start: July 2022

Construction Suspended: November 2022 - July 2023

Anticipated Construction Completion: October 2023

Dewatering During a Sewer Construction Project

Measuring and tracking groundwater levels is a standard practice in ensuring a safe and efficient environment for construction projects that require any underground work, including sewer infrastructure projects.

Groundwater is water that collects or flows beneath the Earth’s surface and is a naturally occurring resource in our region.

During a preliminary design phase of a sewer project, Pierce County Planning and Public Works installs groundwater monitoring equipment along the construction area to track the seasonal changes in groundwater levels.

Using this data, we can anticipate seasonal groundwater trends and stay ahead of potential groundwater issues.

If there is a possibility that the excavation for a sewer construction project will reach the groundwater level, the contractor hired by Pierce County is responsible for developing a dewatering plan before construction begins. The dewatering plan varies by the flow and the amount of water they will be dealing with.

The Parkland/Brookdale Interceptor Phase 3 project will begin in summer 2022, when groundwater levels are lowest. The contractor will have two crews working at the site to accelerate the project to limit the need for dewatering efforts.

While the contractor is excavating and installing the new sewer pipes, there will not be wastewater discharged from the sewer pipes. No fresh groundwater will be contaminated with wastewater. In an event there is a spill, any contaminated water would be directed to the wastewater treatment plant, and the site will be cleaned up.