What’s Happening
Engineering: We are beginning the design engineering for the project which includes collecting field information and creating construction plans.


Environmental: Necessary environmental permits will be obtained.


Surveying: County surveyors will be in the area gathering field data for the project.

About the Project

Planned improvements for the 2022 Asphalt Overlay Program (CRP 5913) involves resurfacing the existing pavement and upgrading existing curb ramps to meet ADA standards at various locations throughout the County. The locations include:


Group 1:
McCutcheon Road East
(Fennel Creek Bridge to Canyon Falls Creek)
Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Group 2:
Sumner Tapps Highway East
(West Tapps Drive East to Auburn City Limits)
Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Group 3:
C Street South
(112th Street South to Park Avenue South)
Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Group 4:
Park Avenue South
(C Street South to Yakima Avenue South)
Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Group 5:

Yakima Avenue South

(Park Avenue South to 96th Street South)


Image of the project vicinity map. Opens in new windowImage of the project.

Group 6:

120th Street East 

(198th Avenue East to South Prairie Road East)


Image of the project vicinity map. Opens in new windowImage of the project.

Group 7:

152nd Street East

(SR 161 to 122nd Avenue East)


Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window

Group 8:

Waller Road East

(72nd Street East to Pioneer Way East) 


Image of the project vicinity map. Opens in new windowImage of the project. Opens in new window
Project Timeline

June 2021 to March 2022: Complete field surveys, prepare construction plans, and contract provisions.

 

April 2022: Advertise for construction bids.

 

Late Spring 2022: Construction expected to begin.

Contact Us

Gregory Hess, P.E.

Design Supervisor

Phone: (253) 798-2283

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409