Project Timeline
December 2021 to March 2022: Complete field surveys.
March 2022 to December 2023: Complete preliminary engineering and right-of-way plans.
December 2023 and Beyond: Right-of-way acquisition, environmental documentation, final plans, specifications, estimates, and construction (currently scheduled for 2025).