Bridge #26211-A Fox Island Bridge Girder Repair (CRP 5949)

FOX ISLAND BRIDGE REPAIR PROJECT

Due to permitting and submittal requirements, the repair project is now expected to begin after October 1, 2023. The Fox Island Bridge girder repair project will focus on degraded bearings on the mainland end of the bridge, Pier 17 and Pier 20. 


  • This work is expected to take 1.5 months to complete.

  • The bridge may be reduced to one lane with alternating traffic during active construction. 

  • Flaggers will direct traffic as needed during work hours. 

  • The bridge will be closed several times for short periods at night during the project. 

  • We will provide notice prior to these short closures including variable message boards. 

  June 2022 Community Meeting

Pierce County Planning and Public Works staff gave updates about this repair project and shared details with the public about plans for a full Type, Size, and Location Study for replacement of the bridge. Get the meeting details and watch the live recording.

  What's happening

Engineering / Construction 
A Contractor is under contract for the construction of this project.

A preconstruction meeting was held with the contractor on Jan. 5, 2023. 

Crews were on the bridge in January to take necessary field measurements for the project. 

Construction on the underside of the bridge is expected to begin in late Fall 2023 due to contract submittal delays. 

Environmental
All environmental permits have been obtained for this project.

Image of the project vicinity map.

Click Image to Enlarge

Image of the project.

Click Image to Enlarge

  About the Project

Planned improvements to the Fox Island Bridge Girder Repair (CRP 5949) include repairing the concrete girder bearings at piers 17 and 20.

  Project Timeline

Fall 2023: Anticipated construction start. 

Fox Island Bridge Contact Information
Andrew Davis, P.E.
Construction Engineering Supervisor
(253) 798-6913

EMAIL
Address
2702 S 42nd St,
Suite 109
Tacoma, WA 98409