What’s happening
264th Street East approximately 900 feet west of 134th Avenue East reopened Aug. 30, 2022 after crews completed a temporary repair at the site of a culvert washout.
The road was closed following a culvert washout on Jan. 7, 2022.
Temporary repair complete
Work on a temporary repair began Aug. 8, 2022 and was completed Aug. 30. Crews installed two temporary 36-inch pipes to allow the channel flow to pass under the roadway, and rebuilt the roadway surface.
Future plans
We planned to install a permanent box culvert in Summer 2022. However, this work has been delayed due to persistently high groundwater levels.
A permanent 16-foot-wide box culvert that supports fish passage is expected to be installed in Summer 2023. Details will be posted on this webpage as they are available.