2023 Road Safety Program - Guardrail and Centerline Rumble Strips (CRP 5948)
What’s Happening
Engineering: We are beginning the design engineering for the project which includes collecting field information, preparing final construction plans and other contract documents to advertise the project for construction.
Environmental: Necessary environmental permits will be obtained.
Surveying: County surveyors will be in the area gathering field data for the project.
About the Project Planned improvements for the 2021 Road Safety Program - Guardrail and Centerline Rumble Strips project involves installing guardrail and centerline rumble strips at various locations throughout the County. The locations include:
Group 1: Sumner Tapps Highway
Install guardrail on the northbound lane between South Tapps Drive East and 36th Street East.
Group 2: Orting Kapowsin Highway East
Install guardrail on the southbound lane between 218th Street East to 214th Street East.
Group 3: Waller Road East
Install centerline rumble strips between Brookdale Road East to the railroad crossing north of Chesney Road East.
Project Timeline
June 2022 to December 2022: Complete field surveying, environmental documentation, construction plans, specifications, and estimates.