Anderson Island Ferry Landing Parking & Holding Lanes (6936)

What’s Happening

Pierce County hosted the Pre-Construction Meeting on July 29, 2022, and issued the Notice to Proceed on August 11, 2022. The Contractor, Sound Pacific Construction. Construction activities began August 15. 


Work hours

Monday - Friday, 7:35 a.m. - 5:30 p.m. (No work will take place on Labor Day or the Friday before Labor Day.)



About the Project
The Anderson Island Ferry Parking and Loading Lanes project is scheduled to begin on August 15, 2022. This project will last until late October and includes repaving, striping, sidewalk improvements, and landscaping.


For further information, visit the Pierce County Ferry page piercecountwa.gov/FerryProjects


Contract Information

Funding



Contract Plans

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

May 11, 2022: Bid Opening date


May 31, 2022: Pierce County awarded the contract to Sound Pacific Construction


July 29, 2022: Pierce County hosted the Pre-Construction Meeting


August 11, 2022:  Notice to Proceed

Contact Us

Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913

Address:

2702 S 42nd St, Ste 109

Tacoma, WA 98409

Sound Pacific Construction
Contractor

Phone: (253) 514-6226

Address:

6708 144th St NW, Ste A

Gig Harbor, WA 98332