New sewer pump station to be built at intersection of 28th Avenue East and 182nd Street East

A project to extend sewer service to a 370-acre area in central Pierce County near Spanaway and Frederickson will begin June 29. The work is expected to be complete by June 2021.

A new sewer pump station will be built near the intersection of 28th Avenue East and 182nd Street East. A pump station collects wastewater and pumps it into a nearby gravity sewer system when it reaches a certain level.

Approximately 2,750 feet of force main will be installed west of the pump station along 28th Avenue East and 183rd Street Court East ending at 22nd Avenue East. Approximately 3,800 feet of gravity sewer line will be installed east of the pump station along 182nd Street East and 38th Avenue East ending at 180th Street East.

Construction work will take place from 7 a.m. to 6 p.m. Monday to Saturday.

Road and lane closures will be required throughout the project. Local, business and emergency access will be provided. Closure information will be shared as it becomes available at www.piercecountywa.gov/28th-ave-pump-station.  

Tucci & Sons Inc. is the contractor for the project. The estimated project cost is $7.25 million and is funded by sewer connection fees.

About the Pierce County sewer system
The Pierce County sewer system collects wastewater from a 117-square-mile area serving 294,000 people in University Place, Lakewood, DuPont, Steilacoom, Milton and a portion of Tacoma. It also serves the unincorporated communities of Parkland, Spanaway, Midland, South Hill, Tehaleh and Frederickson.


MEDIA CONTACT:

Sean McDermott, Pierce County public information specialist

(253) 798-2092

[email protected]

Facebook Twitter Email

Other News in Planning & Public Works

Annual fee changes coming in 2023

Posted on: December 28, 2022

No building inspections on May 24

Posted on: May 9, 2022

Please Continue to Use Online Services

Posted on: January 21, 2022

Annual Fee Changes Coming in 2022

Posted on: December 17, 2021

New septic-to-sewer conversion process

Posted on: November 10, 2021

New application requirement coming Oct. 1

Posted on: September 28, 2021

Apply for a historic preservation grant

Posted on: September 3, 2021

Recording fees increase on July 25

Posted on: July 16, 2021

Development Center Operations Update

Posted on: March 23, 2021

Apply for a historic preservation grant

Posted on: November 24, 2020