News Flash

Planning & Public Works

Posted on: May 18, 2022

144th Street East Sewer Extension project to start May 31

Pierce County will be installing new sewer pipes east of Canyon Road East between 144th Street East and 160th Street East. Construction is scheduled to begin on Tuesday, May 31.

The new system will serve approximately 290 acres of Urban Growth Area that is currently not served by public sewer service. Expanding the sewer utility provides modern services to homes and businesses in the designated urban area and reduces Pierce County’s reliance on septic tanks, which can cause water quality issues over time if not maintained. 

Starting Monday, June 6, 2022, 160th Street East will be closed to through traffic between Canyon Road East and 63rd Avenue Court East. Access for emergency vehicle and local traffic will be maintained at all times. Detour signs will be placed for drivers and pedestrians. 

Project Schedule
This project will be split into eight phases (see map). During the first phase, the contractor will be working six 12-hour days per week, Monday through Saturday. There will be no work on holidays. 

 

Location

Projected Timeline

Closure 1

160th Street East**

May 31 to Aug. 14, 2022

Closure 2

62nd Avenue East by 144th Street East**

Aug. 15-21, 2022*

Closure 3

152nd Street East**

Aug. 22 to Sept. 25, 2022*

Closure 4

62nd Avenue East by 152nd Street East**

Sept. 26 to Oct. 9, 2022*

Closure 5

62nd Avenue East by 160th Street East**

Oct. 10 to Dec. 4, 2022*

Closure 6

152nd Street East**

Dec. 5-23, 2022*

Closure 7

58th Avenue East (north of 152nd Street East)**

Jan. 9-22, 2023*

Closure 8

58th Avenue East (south of 152nd Street East)**

Jan. 23 to March 4, 2023*

* Dates may be subject to change.
 ** Some work, including final pavement restoration, will be completed after all other phased activities are complete.

About the Project
Crews will install approximately:

  • 12,360 feet of gravity sewer pipe
  • 1,150 feet of pressure sewer pipe 
  • 34 concrete manholes
  • Five corrosion resistant manholes
  • One valve vault

A private dryline sewer main located in 58th Avenue Court East will also be connected to the public sewer system.

The authorized budget for this project is $8.1 million and is funded by revenue from connection charges and monthly sewer rates. The project is scheduled to be complete in spring 2023.

Learn more about the project and sign up for email updates at PierceCountyWa.gov/144StreetEast.

#  #  #

MEDIA CONTACT:
Akiko Oda, Pierce County public information specialist
[email protected]
253-798-2092

 

Facebook Twitter Email

Other News in Planning & Public Works

No building inspections on May 24

Posted on: May 9, 2022

Please Continue to Use Online Services

Posted on: January 21, 2022

Annual Fee Changes Coming in 2022

Posted on: December 17, 2021

New septic-to-sewer conversion process

Posted on: November 10, 2021

New application requirement coming Oct. 1

Posted on: September 28, 2021

Apply for a historic preservation grant

Posted on: September 3, 2021

Recording fees increase on July 25

Posted on: July 16, 2021

Inspection Safety Reminder

Posted on: May 3, 2021

Development Center Operations Update

Posted on: March 23, 2021

Apply for a historic preservation grant

Posted on: November 24, 2020

Critical Area Sign-Off Improvements

Posted on: November 19, 2019

October News - Community Plan Updates

Posted on: October 18, 2019