PPW Updates
Lakewood Sewer Main Update, Feb. 1, 2022


Our sewer main repair project on Steilacoom Boulevard in Lakewood is on the home stretch! The contractor working for Pierce County is preparing the road for asphalt pavement and finishing up work for other underground utilities. Meanwhile, crews will be pouring concrete for the sidewalk infrastructure this week. 

In January, the contractor completed the manhole installation and removed the bypass system, which successfully redirected the wastewater flow to the new 120-inch polymer concrete structure and the 36-inch sewer pipe.

Crews are planning to pave the road in the second week of February and install temporary road markings the following week, pending weather conditions. Steilacoom Boulevard is targeted to reopen by the end of the third week of February.

We appreciate the community’s patience and understanding during this project.

Learn more about the Lakewood Sewer Main Repair Project.

Grading vehicles flattening dirt road.
Share on Facebook
Share on Twitter
Share via Email

Copyright © 2021 Pierce County. All Rights Reserved. Privacy Policy
930 Tacoma Ave. South, Tacoma WA 98402

Powered by
CivicSend - A product of CivicPlus