Pierce County plans to extend Canyon Road East from 200th Street East to 208th Street East to increase transportation connectivity for motorists. The county is now finalizing the design and right-of-way acquisitions.

Planned Improvements

  • Extending Canyon Road East from 200th Street East to 208th Street East with one lane in each direction and a two-way left-turn lane.
  • Adding a traffic signal at the intersection of 208th Street East.
  • Modifying the signal at the 200th Street East intersection.
  • Constructing concrete curb, gutter and sidewalk on the west side.
  • Adding street lighting.
  • Constructing stormwater treatment and storage facilities.
Illustration of proposed improvements on Canyon Road East

Project Area

project area for Canyon Road Southerly Extension

Timeline

  • July 2020–Aug. 2020: Right-of-way plans finalized, and preliminary design completed.
  • Aug. 2020–Fall 2022: Prepare construction documents, acquire needed right-of-way, and obtain environmental permits.
  • Late 2022: Advertise for construction bids. Construction expected to start.

Find more information at the project website.

Have a question? Contact Design Supervisor Gregory Hess at [email protected] or call 253-798-2283.

Amy Cruver signature
Amy Cruver Contact information
Share on Facebook
Share on Twitter
Share via Email

Copyright © 2022 Pierce County. All Rights Reserved. Privacy Policy
930 Tacoma Ave. South, Tacoma WA 98402

Powered by
CivicSend - A product of CivicPlus