Work to resurface a section of Point Fosdick Drive Northwest began May 31. Resurfacing work was completed mid-July and crews are waiting on materials to finish the guardrail. Project completion is expected in early September. 

The approximately 1-mile stretch runs from just north of Stone Drive Northwest to approximately 325 feet south of 36th Street Northwest, where Point Fosdick Drive Northwest enters Gig Harbor city limits. 

Image of the project vicinity map.
Image of the project.

About the Project
Planned improvements to Point Fosdick Drive Northwest from Stone Drive Northwest to the Gig Harbor City Limits (CRP 5880) are intended to preserve the existing roadway and restore a smooth surface. 


  • The existing pavement is made of concrete. The pavement will be fractured through a process called crack and seat, which provides a firm and stable base, and then topped with a new layer of asphalt to provide a smooth surface.
  • Crews will install guardrail at several locations through the project area.
Image of the project right-of-way plans cover sheet.

Traffic Impacts

The two-lane road may be reduced to one lane with alternating traffic during work hours. A pilot car may lead motorists through the project area during certain phases of the work.


General work hours will be 7 a.m. to 3:30 p.m. Monday to Friday. During certain phases of the work, work hours may be extended. Information about extended hours will be posted on this webpage.

Contract Information

Funding

The project’s contractor is Miles Resources LLC. The construction cost is approximately $1.25 million. The project is funded with federal Surface Transportation Program funds and County Road Funds.


Contract Plans

Plans, specifications, and bid tabulations for this project are available through the Pierce County Procurement and Contract Services website. Access is provided by going to http://www.piercecountywa.gov/CurrentSolicitations.

Project Timeline

March 23, 2022:  Bid Opening date.

April 7, 2022:  Pierce County awarded the contract to Miles Resources

May 18, 2022:  Pierce County hosted the Pre-Construction Meeting

May 31, 2022:  Notice to Proceed date.

September 2, 2022: Substantial Completion.

September 21, 2022: Physical Completion

Contact Us


Andrew Davis, P.E.

Construction Supervisor

Phone: (253) 798-6913


Miles Resources

Contractor

Phone: (253) 383-3585

Address:

2702 S 42nd Street, Suite 109

Tacoma, WA 98409

Address:

400 Valley Ave NW

Puyallup, WA 98372